City of Lake Forest
Public Works

ANNUAL SLURRY SEAL PROJECT
ZONE B

December 2018 - February 2019

Crack sealing / asphalt repair & Paving / striping & marking removal / slurry sealing
water valve & sewer manhole repair / striping replacement

PROJECT SCHEDULE

DURING INCLEMENT WEATHER OR OTHER EMERGENCIES:
“No Parking” Signs Will Be Removed and You Will Receive Another Notice as to When Your Street Will Be Rescheduled

 

FROM

TO

WORK TYPE

 

Monday, February 11

Friday, February 15

Slurry Sealing

 

TBD

TBD

TBD

TBD

Water Valve/Sewer Manhole Repair

Replace Striping

 

To see project details
 click the enlarge icon located in the top right corner “[ ]” on the map below.

 
 
 

PROJECT DETAILS & CONTACT INFORMATION

The City of Lake Forest will be slurry sealing Zone B to ensure a safe, smooth roadway surface and make certain the roadways last as long as possible. The schedule allows for on-street parking within 1,000 feet from any home impacted by that day's work. Slurry sealing will occur during the week, except on trash pick-up days.  

This project will be completed in four general phases:

  • First, a crew will be in the streets crack sealing. This activity will place sealant in cracks that meet specific criteria, not necessarily every crack.

  • Second, a pavement repair crew will complete spot repairs of the areas that have the greatest deterioration. These areas have already been identified by the City. 

  • Third, a crew will place slurry over the entire streets. 

  • Fourth, a crew will re-strip pavement markings.

Throughout the process there will be various parking restriction and traffic control signs, please adhere to all posted signage and posted web map information. Trash will be picked up on the normal pickup schedule. The contractor, Doug Martin Contracting Co., will notify you via door hangers seven days prior to work, and again 24 hours prior.

The City’s goal is to provide good, quality roads for our residents. This will require the City to interrupt you normal routines while the project is under construction. The City is will be working to get you back to your normal routines as quickly as possible. 

 WE APPRECIATE YOUR PATIENCE & COOPERATION THROUGH THIS PROCESS OF REVITALIZING YOUR NEIGHBORHOOD ROADS

For general project information, please call:

(844) MYCITY5 or (844) 692-4895

Or visit the City’s project website:

http://www.lakeforestca.gov/900/Road-Construction

For the duration of this project, the City has contracted with:
Dough Martin Contracting Co., Inc.
For any questions please contact:
Taylor Abernathy
Principal Civil Engineer
(714) 461-3490
Douglas Erdman
Assistant City Engineer/Engineering Services Manager
(714) 282-5233