2018 Street Slurry Seal and Rehabilitation
City of Laguna Beach

PUBLIC WORKS

AUGUST 2018 - NOVEMBER 2018

CANYON ACRES DRIVE, ARROYO DRIVE, WOODLAND DRIVE, LAGUNA CANYON FRONTAGE ROAD, and NEIGHBORHOODS BOUNDED by THALIA STREET, TEMPLE TERRACE, CRESS STREET, and the coast

PROJECT SCHEDULE

DATE

PROJECT WORK

STREETS

Monday, October 15

Striping & Pavement Markings

Frontage Road
Canyon Acres
Arroyo Drive

Tuesday, October 16

Curb Markings & Reflective Markers

Projectwide

Wednesday, October 17

Curb Markings & Reflective Markers

Projectwide

Thursday. October 18

Curb Markings & Reflective Markers

Projectwide

roadwork scheduled time
7am - 5pm 

To see project details about your street, click the enlarge icon located in the top right corner " [ ] " on the map below, then click on your street.

 
 

CLICK THE PDF LINKS AT THE BOTTOM OF THE PAGE FOR NOTIFICATIONS

PROJECT DETAILS & CONTACT INFORMATION

  • Locations of pavement repairs will be painted in orange and pink paint in July.

  • Preliminary work consisting of drainage improvements, localized pavement repairs, and crack sealing, is expected to occur during August and September.

  • Roadway slurry seal application and re-striping in September and October.

      The slurry seal provides a protective coating for the streets and it is designed to seal and extend the life of the pavement. On the day the slurry seal is applied, the street will most likely be closed entirely to vehicles and pedestrians. Detours may be necessary. Several streets will be resurfaced each day, so your street may close as early as 7:30 a.m. or as late as 1:30 p.m. It takes approximately 4 hours for the slurry seal to dry for vehicle use, and about 2 hours for pedestrian use.

     “NO Parking” signs will be posted within the work areas prior to roadway closures. Trash collection and mail delivery services may occur at different times of the day, but will not be interrupted. Emergency access will be provided at all times.

     Excel Paving, the City’s contractor, will make every effort to maximize access to properties whenever possible. All impacts and closures will be minimized to the greatest extent possible.

 WE APPRECIATE YOUR PATIENCE & COOPERATION THROUGH THIS PROCESS OF REVITALIZING YOUR NEIGHBORHOOD ROADS

For general project information, please call:

(844) LAGUNA4 or (844) 524-8624

Or visit the City’s project website:

http://www.lagunabeachcity.net/slurryseal

DOCUMENTS

General Project Mailer (Mailed July 2018)

Preparatory Repair Work Notice

Slurry Seal Notice

Postponement Slurry Seal Notice

 