Clark Avenue Rehabilitation Project
OE provided design engineering services to the City of Bellflower on the Clark Avenue Rehabilitation project. The project spanned 2,200 LF of arterial roadway from Artesia Boulevard to the South City limits. The scope of work included an inverted grind and overlay to reduce the crown height and provide more gradual grads at the edge of the roadway. The project also entailed a full-width ARHM overlay, localized full-depth reconstruction, installing 22 traffic loops, adjusting 22 manholes and 35 valves, metal hand-railing, curb & gutter, PCC driveways, and 11 curb ramp replacements to meet ADA compliance, as well as necessary traffic striping. Due to the projects close proximity to the City of Lakewood, OE was required to coordinate with both the City of Bellflower and the City of Lakewood.