Athena-Omega Neighborhood

CITY OF ANAHEIM PUBLIC WORKS

RESIDENTIAL STREET IMPROVEMENT PROJECT

august 2016 - august 2016

Project Area

(To see project details about your street click the enlarge icon " [ ] " on the map below, then click on your street!)

SLURRY SCHEDULE: Sept. 1-2, 2016 - SEE MAP FOR PARKING AND DRIVING RESTRICTIONS.  

Updated: August 16, 2016 at 11:19 A.M.

GRINDING SCHEDULE: AUGUST 8-9, 2016 - SEE MAP FOR PARKING AND DRIVING RESTRICTIONS.

Updated:August 2, 2016 at 10:19 A.M.

 

PAVING SCHEDULE: August 9-10, 2016 - SEE MAP FOR PARKING AND DRIVING RESTRICTIONS.

Updated:August 2, 2016 at 10:19 A.M

AN INSIDE LOOK AT THE ANaHEIM STREET PAVING PROGRAM

For more information call: 1-844-528-4362 (1-844-5ATHENA)

For a Printable Version Click Here

Athena-Omega website.jpg